Adirondack Welcome Center

Queensbury, Warren County, NY

Mar 2018 - Aug 2018

Untitled design (32).png

Gateway to the Adirondack region of New York State

Untitled design (32).png

Finished ahead of schedule and on budget despite redesigns

Untitled design (32).png

Over 1000 average daily vehicles served

The Details


The Adirondack Welcome Center was constructed in Queensbury, Warren County, New York. The facility on New York’s Interstate 87 North was a Governor Andrew Cuomo Executive Priority Project and a high-profile Best-Value project for New York State Department of Transportation (NYSDOT). This complex facility had to be delivered in 6 months while maintaining public use throughout construction.


In response to the complexity of the project and owner’s requirements, The Wesson Group (TWG) leveraged its joint venture with Harrison & Burrows Bridge Constructors, known as HBTWG JV LLC, and hired a vertical construction manager to be integrated into the team as a subconsultant.


Scope of Work

  • Replacement of the existing 8,615-square-foot building

  • Demolition and hazardous waste abatement of the existing facility

  • Clearing and grubbing

  • Erosion control

  • Site work to raise the building footprint

  • New passenger car and over-the-road truck parking lots

  • New septic systems fields, pump stations, and associated infrastructure

  • Extensive curbing, sidewalk, and walk-of-fame outdoor features

  • Restrooms, interactive I LOVE NY kiosks, stone fireplace, and an office for the State Police

  • Geothermal heating and cooling, LED lighting package, and electric car charging availability

  • Heavy timber framing with both steel trusses, SIP panels and custom heavy glulam timbers

  • Outdoor play area with ADK-themed children’s fire tower and zip line and a pet comfort area.

  • NYSDEC boat inspection/decontamination station, to control spreading of invasive species.


Peak Daily Operations

  • 105 HBTWG/subcontractor workers

  • 40 subcontractor companies

  • Project Labor Agreement

  • Extensive MWBE utilization goals

  • 6-month delivery window April – September



The Challenge


During construction, hundreds of engineering and architectural changes, redesign packages, and change-order requests threatened to impede progress.



The Result


Working closely with NYSDOT and the engineer of record, the HBTWG JV partnership was able to expedite the changes and implement several redesigned structural elements of the building through the use of several acceleration packages—all of which allowed the Welcome Center to open ahead of the contracted schedule date and finish under the awarded budget.